Tunnel under Gent-Dampoort railway line - Ghent
Description 
    The construction project involves the construction of a new cycle and pedestrian tunnel under the railway line, a new coach park and work in the surrounding areas at the Gent-Dampoort station. A new tunnel is being built under the track to create a safer cycling connection. The cycle paths are largely being installed using a concrete U-passage. The new tunnel under the track is realised using the box jacking method, with the tunnel going through the railway embankment. The jacked tunnel is 23m long.
Â
News
26/04/2019 - 15:30
  05/03/2018 - 14:30
  location 
    Project Details
                        Contractor                    
                    
                Station Gent-Dampoort, Gent, Oost-Vlaanderen, Belgium
                     
                    Client 
    Stad Gent
      Engineering Office 
    Sweco
      Span 
    23m
      Surface area subterranean 
    1 200m²
      Construction period
1 year 1 month
Start work
03-2018
End of work
04-2019
 
                    






 
                                       